Elemental Energy is investigating a new wind energy project opportunity near the town of Parrsboro and within the municipal boundaries of Cumberland.  The proposed project is being investigated as a candidate project for Nova Scotia’s recently announced renewable energy procurement opportunity, the Green Choice Program.

Questions?

Location

Parrsborro, Nova Scotia

Size

150 MW

Timing

Start of Construction 2025

Roles

Developer / Owner

QUESTIONS?

If you have any questions, comments or interests, please contact Elemental Energy’s team via the following:

development@elementalenergy.ca
1.604.648.6630

Project Location

Register For New Prospect Wind Project Updates

Project Schedule

2023
  • Undertake project feasibility studies
  • Project Notification / Introduction to Community
  • Community Engagement Activities (ongoing)
Early to Mid 2024
  • Community Engagement (ongoing)
  • Initiate Environmental Field Studies
  • Bid project into Green Choice Program
Mid to Late 2024
  • Community Engagement (ongoing)
  • Green Choice Program Award, execute PPA if successful
  • Complete Environmental Field Studies, Register Environmental Assessment
2025
  • Community Engagement (ongoing)
  • Municipal and Other Permitting
  • Construction Begins
2027
  • Community Engagement (ongoing)
  • Commence Operations

Project Documents